PMP MCQ Questions and Answers
Practice ModeShowing 10 of 406 questions
Q271
Which of the following is LEAST likely to improve the accuracy of cost estimates produced through parametric cost estimating technique?
Answer: Option C
Q272
You are in the process project a project schedule for repainted your house, you first need to scrap off the existing paint, and then add a layer of primer. The primer provides the paint a better bonding surface so it sticks to the base material much better. Without priming, drywall surfaces will soak up more finish paint in some areas than in others, producing a splotchy effect. You decided to speed up the process by starting priming before all the scraping is finished. However once the primer i
Answer: Option D
Q273
You are the project manager at a utility company. Due to the recent
rise in the cost of petroleum, your organization is exploring cheaper,
alternative forms of energy. You have just completed the project scope changes, requested changes, and updates to the project scope management plan. Which of the following process did you just
complete?
Answer: Option A
Q274
Which of the following best describes project funds that are held in reserve to account for and offset known risks, such as project scope risks, schedule risks, cost or quality risks?
Answer: Option A
Q275
You are in the process of identifying and documenting project risks. Which of the following statements are true?
Answer: Option B
Q276
Which of the following is the total amount of time that a scheduled activity may be delayed from its early start date without delaying the project finish date?
Answer: Option A
Q277
Which of the following process is involved in developing an approximation of the costs of the resources needed to complete project activities?
Answer: Option B
Q278
Which of the following processes involves analyzing activity sequences, activity duration, and resource requirements, to develop the project schedule?
Answer: Option B
Q279
You are involved in monitoring specific project results to determine whether they comply with relevant quality standards. You are suing the control chart to illustrate how the process is behaving over time. You have constructed your control chart and that all data points are
within upper and lower control limits of chart. In addition, seven consecutive data points re observed, to be on one side of the mean. Which of the following is your BEST plan of action?
Answer: Option D
Q280
You are in the process of obtaining the necessary human resource to complete the project. Which of the following are not the outputs of this process?
Answer: Option D