Q221
You are the project manager responsible for renovating a 70-year old office building. You intend to hire an outside construction firm to seismic retrofit the building in order to make that the building can with stand large earthquakes. You are in the process of selecting a contract type best suited for this project. You would like to select a contract type that transfers the risks onto the seller for any cost risk and nonperformance issues. Which contract type should you choose?
Answer: Option D
Q222
All of the statements regarding decision tree analysis is true EXCEPT:
Answer: Option C
Q223
Qualitative risk analysis requires accurate data as its input. Risk Data
Quality Assessment is a technique to evaluate the degree to which the data regarding risks would be useful. What is the best course of action if the Risk Data Quality Assessment for most of the identified risks are low?
Answer: Option A
Q224
Which of the following are not tools/ techniques that can be used to create the WBS?
Answer: Option A
Q225
Which of the following statements are true regarding Management Reserves?
Answer: Option B
Q226
You are currently in the process of prioritizing risks by their impact or probability of occurrence. Which of following tools/ techniques are LEAST useful?
Answer: Option B
Q227
All of the following statements regarding Control Accounts are true EXCEPT:
Answer: Option C
Q228
Keeping up with the growth was becoming a problem for a privately owned Chinese financial services company. Although it easily lured business from state-owned competitors, low skill levels and weak
accounting systems threaten the company
Answer: Option C
Q229
You are in the process of establishing a total cost baseline for measuring project performance. All of the following are outputs of this process EXCEPT:
Answer: Option C
Q230
You are the project manager for a construction company. Your firm has been contracted to complete the construction of a 10-story office building. This project will use three point estimates to calculate the estimates for activity duration. You have the following estimates for
task A (creating the foundation). Assuming the triangular distribution what is the average duration
estimate based on the following three point estimates?
Pessimistic= 100 days
Optimistic= 40 days
Most likely=65 days
Answer: Option D