Q191
You are in process of controlling changes to the project cost baseline. All of the following are outputs of this process EXCEPT:
  • A WBS updates, WBS dictionary updates
  • B Lessons learned, project management plan updates
  • C Requested changes, recommended corrective actions
  • D Cost estimates updates, cost baseline updates
Answer: Option A
Q192
You are in process of exterminating which set of project activities will take the longest to complete. Which of the following is the MOST appropriate tool to use?
  • A Milestone chart
  • B WBS
  • C RBS
  • D Network diagram
Answer: Option D
Q193
You are a project manager responsible for constructing a new sports arena in preparation of the upcoming Olympics. Construction began on the project a year ago. The stakeholder of the project want a status report on the performance of the project to the date. Unfortunately, you are afraid of telling your stakeholders that your project is coming in over the budget and the cost change is required using the cost change control system. Which of the following tools were used to calculate the cost var
  • A Performance measurement analysis
  • B Project management software
  • C Parametric estimating
  • D Performance reports
Answer: Option A
Q194
Ishikawa diagrams are used in which of the following processes?
  • A Perform quality control
  • B Create WBS
  • C Schedule development
  • D Risk management planning
Answer: Option A
Q195
You are the Chief Technology Officer of a major stock exchange. You are in the charge of the project to reengineer the organization
  • A Add contingency reserves into overall project schedule to plan for any potential change requests
  • B Contact the stakeholder to dissuade him from submitting un necessary change request
  • C Contact the stakeholder
  • D Involve the stakeholder in the project as early as possible
Answer: Option D
Q196
Which of the following best describes the conflict resolution technique that involves problem solving and fact-finding missions in order to discuss a win-win resolution?
  • A Withdrawal
  • B Forcing
  • C Confrontation
  • D Smoothing
Answer: Option C
Q197
Which of the following statements regarding configuration management system is least true?
  • A Configuration management systems establish a method to consistently identify and request changes to established baselines
  • B Configuration management systems provide mechanisms to communicate changes to all stakeholders
  • C Configuration management systems provide mechanisms to communicate changes to all stakeholders
  • D Configuration management systems provide opportunities to improve project by considering impact of changes
Answer: Option C
Q198
Which of he following best describes the risks that still remain after avoidance , transfer, or mitigation responses have been implemented?
  • A Contingency risks
  • B Tertiary risks
  • C Residual risks
  • D Secondary risks
Answer: Option C
Q199
With respect to earned value analysis, which of the following is the value of work actually completed?
  • A Actual cost(AC)
  • B Planed value(PV)
  • C Cost variance(CV)
  • D Earned value(EV)
Answer: Option D
Q200
Which of the following illustrate a chart with upper /lower limits on which value of some statistical measure for a series of samples aren plotted using sample measure measurement, where the mean and standard deviation are determine from the sample selected?
  • A Statistical sampling
  • B Gantt chart
  • C Pareto diagram
  • D Control chart
Answer: Option D