PMP MCQ Question and Answer

PMP MCQ Question and Answer
401. Which of the following consists of tools and techniques used to gather, integrate, and disseminate the outputs of the project management processes?
  • EVM
  • PDM
  • WBS
  • PMIS
Show Answer
402. You are the project manager at the Java Ice Cream Factory. You are currently supervising the manufacturing of a new flavor of ice cram JavaBean Burgundy Crunch. The manufacturing of this new flavor was proceeding as planned, until a manufacturing error occurred that requires corrective actions to be taken. To ensure the effectiveness of corrective actions, corrective actions frequently require which of the following?
  • Resource leveling
  • Rebaselining project schedule baseline
  • Performance measurements
  • Root-cause analysis
Show Answer
403. All of the following statements are TRUE regarding ground rules EXCEPT:
  • Ground rules area tools/ techniques of develop project team process
  • Ground rules are a list of acceptable and unacceptable behaviors adopted by project team.
  • All project team members share responsibility for enforcing the ground rules
  • Ground rules help to authorize and define the scope of a new phase or project.
Show Answer
404. You are in the process of reviewing all change requests and controlling changes to deliverables and organizational process assets. All of the following are INPUTS except:
  • Work performance information
  • Recommended preventive actions and corrective actions
  • Requested changes
  • Forecasts
Show Answer
405. Which of the following BEST describes the procedures by which the project schedule can change, and includes the paperwork, tracking systems, and approval levels necessary for authorizing changes?
  • Schedule change control system
  • None of the statements are correct
  • Integrated change control
  • Schedule comparison bar charts
Show Answer
406. The administrative closure procedure is an output of the close project process. It is an input to which process?
  • Manage stakeholders
  • Integrated change control
  • Direct and manage project execution
  • Contract closure
Show Answer
Questions and Answers for Competitive Exams Various Entrance Test