PMP MCQ Question and Answer

PMP MCQ Question and Answer
381. You are a project manager responsible for constructing a new sports arena in preparation of upcoming Olympics. Construction begins on the project over a year ago. The stakeholder of a project wants a status report on the performance of the project to date. Unfortunately you are afraid to tell your stakeholders that your project is coming in significant behind schedule. In fact schedule delays are so severe that the rebaselining of the project schedule is required. Which of the following statemen
  • Rebaselining is used as your first resort in controlling the schedule
  • Approval from all stakeholders is required prior to rebaselining the schedule
  • Historical data may be removed when you rebaseline the schedule
  • None of the choices are correct
Show Answer
382. All are the part of scope baseline except:
  • Project scope statement
  • WBS
  • WBS dictionary
  • Corrective actions
Show Answer
383. Risk monitoring and control process involves all of the following except:
  • Quantifying the possible outcome for the project and their probabilities
  • Reanalyzing existing risks
  • Monitoring trigger for contingency plan
  • Reviewing execution of risk Reponses
Show Answer
384. You are a project manager at java ice cream factory. You are currently supervising the manufacturing of new flavor ice cream java bean, burgundy crunch. The manufacturing of this flavor was proceeding as planned, until a manufacturing error occurred that requires corrective action to be taken. Ironically the manufacturing error resulted in a new variant of the flavor. Product team really thinks that flavor would be a success in a marketplace. They have asked you to cancel the corrective action
  • Workarounds are used to correct problems that occur with changes in the project scope
  • Changes to the product scope should be in the project scope
  • Changes to the product scope are a result of implementing corrective actions
  • Changes to the product scope are defined in the integrated change control plan
Show Answer
385. You are a project manager for a company that sells online music. Your project is to develop a new content management system that will not only manage all users purchase downloads, but will automatically learn the users music interests in order to make future product recommendations. In addition your content management system must scale to support millions of concurrent music downloads a day. Your team has made significant progress on the project. You are preparing the performance of a project to
  • The CV is positive number, which implies that your project is under budget
  • The CV is positive number, which implies that your project is over budget
  • The CV is negative number, which implies that your project is under budget
  • The CV is negative number, which implies that your project is over budget
Show Answer
386. Which of the following statements are true regarding project risk management?
  • None of the statements are true
  • Qualitative risk analysis involves numerically analyzing the impacts of identified risks
  • Risk monitoring and control involves tracking identified risks and executing risk response
  • Risk identification involves how to plan and execute risk management activities
Show Answer
387. Which of the following statements are true regarding cost and schedule variances?
  • The amount of variance of CV and SV values tend to increase as the project reaches completion
  • The amount of variance of CV and SV values remain the same as the project reaches completion
  • Schedule variance will ultimately equal to cost variance when project is completed
  • The amount of variance of CV and SV values tend to decrease as the project reaches completion
Show Answer
388. You are the project manager for the company that sells online music. Your project is to develop a new content management system that will not only manage all users purchases and downloads, but will automatically learn the users music interests in order to make future product recommendations. In addition your content management system must scale to support millions of concurrent music downloads a day. Your team has made significant progress on the project. You are preparing the performance of a
  • 1.333
  • 0.875
  • 1.14
  • 1.16
Show Answer
389. Which of the following statements are false regarding the cost change control system?
  • It defines the procedures by which the cost baseline may be changes
  • It defines the approval level necessary for authorizing the changes
  • It provides information on the project scope and cost performance, such as which budgets have been met and which are not.
  • Integrated change control system
Show Answer
390. Which of the following statements are NOT techniques used to resolve conflicts on a project?
  • Directing, smoothing
  • Forcing, smoothing
  • Compromise, confrontation
  • Withdrawal, forcing
Show Answer
Questions and Answers for Competitive Exams Various Entrance Test