PMP MCQ Question and Answer
PMP MCQ Question and Answer
81. All of the following statements are true regarding Simulation and Monte Carlo analysis EXCEPT:
- The output of simulation is a probability distribution (i.e total costs or completion dates)
- Modeling and simulation are recommended for use in cost and risk analysis because they are more powerful and less subject to misuse than EMV analysis
- None of the choices are correct
- For cost risk analysis, a simulation can use the project WBS or cost breakdown structure as its model
82. Earned value analysis is a performance reporting tool/ technique. Which of the following best describes earned value (EV)?
- Value of the work completed
- Portion of approved cost estimate planned to be spent
- Total of costs incurred in performing work activity
- Efficiency indicator to reflect cost performance of project
83. Which of the following statements are true regarding project endings?
- Integration occurs when a project evolves into ongoing operations
- Completion occurs when the project end because it was completed successfully and accepted by stakeholders
- Addition occurs when the resources (personnel, equipment,property, etc) of the project are reassigned to other areas within the organization or other projects
- None of the choices are correct
84. All of the following are inputs to the Close Project process EXCEPT:
- Administrative closure procedure
- Project management plan
- Deliverables
- Work performance information
85. A SPI < 1 indicates which of the following?
- Project is ahead of schedule
- Project is over budget
- Project is under budget
- Project is behind schedule
86. Contract documentation is an input to the Contract Closure Process. It includes all of the following EXCPT:
- Payment record
- Approved changes requests
- Contract closure procedure
- Supporting schedules
87. All of the following statements are true EXCEPT:
- Project closure documents and project files are outputs of the Close Project Process
- The formal acceptance documentation formally indicates that the customer or sponsor has officially accepted the project deliverables
- The project closure documents provide formal documentation indicating the completion of project and transferring of project deliverables to others
- None of the choices are correct
88. Procurements audits are a tool/ technique of which of the following processes?
- Request Seller Responses
- Select Sellers
- Plan Purchases And Acquisition
- Contract Closure
89. Performing the administrative closure process includes all of the following EXCEPT:
- Gather lessons learned
- Archive project information
- Review and approve requested changes
- Analyze project success or failure
90. According to the PMI, which of the following best describes
- Reviews at the conclusion of a project phase to determine whether the project should continue
- Assignment of additional resources to the project in an attempt to decrease the project timeline/ schedule
- Process of exceeding the specified project requirements
- Schedule compression by starting a new task/ phase prior to completing the current project tasks.