PMP MCQ Questions and Answers
Practice ModeShowing 10 of 406 questions
Q21
Your project sponsor has asked you to produce a Risk Management Plan for your current project. Which of the following best describes how you should tailor the plan to your project?
Answer: Option B
Q22
facturer of electronic components. Your company had been a long time market leader in electronic components distribution industry. However, in recent years,
the Internet has transformed the competitive landscape. As a result company
Answer: Option A
Q23
Reverse analysis is a tool/ technique in ll of the following processes
EXCEPT:
Answer: Option B
Q24
Monte Carlo analysis is a form of what type of analysis?
Answer: Option C
Q25
You have been hired as a project manager for a small local bank. The bank wants you to design and develop custom online bill pay software so that its customers can pay their bills online. You are ready to begin the Activity Resource Estimation process for your project. Which of the following would you NOT consider when developing the activity resource requirements document?
Answer: Option C
Q26
A project schedule can be presented in various formats. All of the following are valid formats of the project schedule EXCEPT:
Answer: Option D
Q27
All of the following statements are true regarding the Activity Sequencing / Activity Duration Estimation process EXCEPT:
Answer: Option A
Q28
Your project team has already created the WBS, developed estimates for the work packages, and sequenced the project activities using the arrow diagramming method. In addition, your team has applied resource leveling and schedule compression techniques on the project schedule. Which actions should be performed NEXT:
Answer: Option A
Q29
You are the project manager responsible for developing a new hybrid engine for a major auto manufacturer. You are in process of developing the project schedule. In order to manage the uncertainty associated with the project schedule, you intend to do the following:
(a) use average task duration estimates; (b) schedule backwards from the date a project is needed (to ensure work that needs to be done is done, and it is done only when it is needed; (c) place
aggregate buffers in the project plan
Answer: Option A
Q30
Which of the following process involves determining project roles, responsibilities, and reporting relationships, and develops the staffing management plan?
Answer: Option B