PMP MCQ Questions and Answers
Practice ModeShowing 10 of 406 questions
Q71
All of the following statements are true regarding the critical path method EXCEPT:
Answer: Option A
Q72
You are the project manager for a large children
Answer: Option D
Q73
You are using the three-point estimating technique to estimate the duration of a schedule activity. You are given the following data:
[Pessimistic=100days] | [optimistic=40days] | [most likely=65 days]
Which of the following statements are true?
Answer: Option D
Q74
You are in the process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the LEAST helpful input?
Answer: Option D
Q75
You are in process of analyzing the effects of identified risks. Which of
the following is the LEAST helpful input?
Answer: Option C
Q76
You are the project manager at an auto manufacturer. Due to the recent rise in the cost of petroleum, the market demand for hybrid cars with high fuel efficiency has increased. Your company has identified the multi-billion dollar market opportunity for highly fuel efficient vehicles.
However, your organization does not have enough resources and expertise to exploit this opportunity. Hence, your organization has decided to identify the qualified candidates. Which of the following best describes
Answer: Option C
Q77
Which of the following statements are FALSE regarding rolling wave planning?
Answer: Option D
Q78
Which of the following risks should be classified as a force measure risks?
Answer: Option D
Q79
Which of the following processes involves developing necessary procedures to mitigate threats to the project from the project risks?
Answer: Option D
Q80
Which of the following can be used to determine what work is included in each work package for each of your team members?
Answer: Option D