PMP MCQ Questions and Answers

Practice Mode
Showing 10 of 406 questions
Q81
All of the following statements are true regarding Simulation and Monte Carlo analysis EXCEPT:
  • A The output of simulation is a probability distribution (i.e total costs or completion dates)
  • B Modeling and simulation are recommended for use in cost and risk analysis because they are more powerful and less subject to misuse than EMV analysis
  • C None of the choices are correct
  • D For cost risk analysis, a simulation can use the project WBS or cost breakdown structure as its model
Answer: Option C
Q82
Earned value analysis is a performance reporting tool/ technique. Which of the following best describes earned value (EV)?
  • A Value of the work completed
  • B Portion of approved cost estimate planned to be spent
  • C Total of costs incurred in performing work activity
  • D Efficiency indicator to reflect cost performance of project
Answer: Option A
Q83
Which of the following statements are true regarding project endings?
  • A Integration occurs when a project evolves into ongoing operations
  • B Completion occurs when the project end because it was completed successfully and accepted by stakeholders
  • C Addition occurs when the resources (personnel, equipment,property, etc) of the project are reassigned to other areas within the organization or other projects
  • D None of the choices are correct
Answer: Option D
Q84
All of the following are inputs to the Close Project process EXCEPT:
  • A Administrative closure procedure
  • B Project management plan
  • C Deliverables
  • D Work performance information
Answer: Option A
Q85
A SPI < 1 indicates which of the following?
  • A Project is ahead of schedule
  • B Project is over budget
  • C Project is under budget
  • D Project is behind schedule
Answer: Option D
Q86
Contract documentation is an input to the Contract Closure Process. It includes all of the following EXCPT:
  • A Payment record
  • B Approved changes requests
  • C Contract closure procedure
  • D Supporting schedules
Answer: Option C
Q87
All of the following statements are true EXCEPT:
  • A Project closure documents and project files are outputs of the Close Project Process
  • B The formal acceptance documentation formally indicates that the customer or sponsor has officially accepted the project deliverables
  • C The project closure documents provide formal documentation indicating the completion of project and transferring of project deliverables to others
  • D None of the choices are correct
Answer: Option D
Q88
Procurements audits are a tool/ technique of which of the following processes?
  • A Request Seller Responses
  • B Select Sellers
  • C Plan Purchases And Acquisition
  • D Contract Closure
Answer: Option D
Q89
Performing the administrative closure process includes all of the following EXCEPT:
  • A Gather lessons learned
  • B Archive project information
  • C Review and approve requested changes
  • D Analyze project success or failure
Answer: Option C
Q90
According to the PMI, which of the following best describes
  • A Reviews at the conclusion of a project phase to determine whether the project should continue
  • B Assignment of additional resources to the project in an attempt to decrease the project timeline/ schedule
  • C Process of exceeding the specified project requirements
  • D Schedule compression by starting a new task/ phase prior to completing the current project tasks.
Answer: Option A
Questions and Answers for Competitive Exams Various Entrance Test