Q351
You are the project manger at a utility company. Due to the recent rise in the cost of petroleum, your organization is exploring cheaper, alternatives forms of energy. You are in the process of developing the project charter. All of the following are tools/ techniques that you can
use to develop the project charter EXCEPT:
Answer: Option C
Q352
You are the project manager for a large children
Answer: Option D
Q353
You are the project manager at Happy Coffee Café, a rapidly growing franchise selling premium blended coffee. Currently, your company is planning on opening additional stores through the United states. Your target markets primarily include densely populated metropolitan areas. Your company is evaluating different areas for expansion, including New York, San Francisco, and Seattle. Based on your market analysis you have obtained the following information: New York-IRR (33%), payback period (1.5
Answer: Option C
Q354
Which of the following statements are true regarding straight line depreciation?
Answer: Option A
Q355
Which of the following is NOT a valid reason to authorize a project?
Answer: Option A
Q356
Which of the following statements are TRUE regarding the difference between a project expeditor and project coordinator roles?
Answer: Option C
Q357
You have been assigned to a project to build the largest U.S. natural gas pipeline project in more than 20 years. The proposed 1,350-mile, 42-inch diameter pipeline will provide valuable infrastructure allowing producers in the Rocky Mountain region to deliver their natural gas to
attractive markets in the Midwest and northeastern parts of the U.S. You are in the project planning process where you are involved in identifying the specific schedule activities that need to be performed to produce
Answer: Option D
Q358
You are the project manager for an information technology division of a large financial services firm in the United States. Your company offers a web based trading platform that provides options and futures trading for U.S commodities markets. Due to the rise in popularity of futures and options trading, your company has grown rapidly. In fact, due to rapid growth, the company
Answer: Option B
Q359
You are the project manger at XYZ Software Corp, a U.S software company developing enterprise Human Resources Applications. You
Answer: Option B
Q360
Which of the following statements about fast-tracking is TRUE?
Answer: Option C