Q381
You are a project manager responsible for constructing a new sports arena in preparation of upcoming Olympics. Construction begins on the project over a year ago. The stakeholder of a project wants a status report on the performance of the project to date. Unfortunately you are afraid to tell your stakeholders that your project is coming in significant behind schedule. In fact schedule delays are so severe that the rebaselining of the project schedule is required. Which of the following statemen
Answer: Option C
Q382
All are the part of scope baseline except:
Answer: Option D
Q383
Risk monitoring and control process involves all of the following except:
Answer: Option A
Q384
You are a project manager at java ice cream factory. You are currently supervising the manufacturing of new flavor ice cream java bean, burgundy crunch. The manufacturing of this flavor was proceeding as planned, until a manufacturing error occurred that requires corrective
action to be taken. Ironically the manufacturing error resulted in a new variant of the flavor.
Product team really thinks that flavor would be a success in a marketplace. They have asked you to cancel the corrective action
Answer: Option B
Q385
You are a project manager for a company that sells online music. Your project is to develop a new content management system that will not only manage all users purchase downloads, but will automatically learn the users music interests in order to make future product recommendations. In addition your content management system must scale to support millions of concurrent music downloads a day. Your team has made significant progress on the project. You are preparing the performance of a project to
Answer: Option A
Q386
Which of the following statements are true regarding project risk management?
Answer: Option C
Q387
Which of the following statements are true regarding cost and schedule variances?
Answer: Option D
Q388
You are the project manager for the company that sells online music. Your project is to develop a new content management system that will not only manage all users purchases and downloads, but will
automatically learn the users music interests in order to make future product recommendations. In addition your content management system must scale to support millions of concurrent music downloads a day. Your team has made significant progress on the project. You are preparing the performance of a
Answer: Option B
Q389
Which of the following statements are false regarding the cost change control system?
Answer: Option C
Q390
Which of the following statements are NOT techniques used to resolve conflicts on a project?
Answer: Option A