PMP MCQ Questions and Answers
Practice ModeShowing 10 of 406 questions
Q391
Which of the following s most likely to require a rebaselining in order to provide a realistic measure of performance?
Answer: Option D
Q392
One of your friends is a manager at telecommunications company. She is currently managing a project developing a VoIP (Voice over IP) gateway that addresses the challenges facing service providers
deploying packer-based voice networks. The gateway offers a comprehensive approach to implementing high-density carrier-class voice over packet gateway applications. She is in the process of
developing the project schedule, and has determined that the project has 4 critical paths. Which of the follow
Answer: Option D
Q393
You are the project manager within a large multi-national company. Your current project involves a large software development project that involves coordination of resources across four different
reengineering teams across three different countries. Specifically your UI team is based in India, your database team and middleware team is in U.S., and your QA team is in Canada. The engineers in each of the team report to geographic functional manger, but are currently on loan
to you for your proje
Answer: Option D
Q394
You are in the process of controlling changes to the project cost baseline. Which of the following is the LEAST helpful tool/ technique?
Answer: Option C
Q395
Which of the following statements are FALSE regarding project time management?
Answer: Option C
Q396
The applied level of change control is LEAST dependent upon:
Answer: Option D
Q397
Which of the following calculates the difference between the budget at completion and estimate at completion?
Answer: Option B
Q398
Approved corrective actions are an input to which process?
Answer: Option B
Q399
Change control system, variance analysis, replanning and configuration management systems are tool/ techniques of which process?
Answer: Option B
Q400
You are project manager responsible for constructing a new sports arena for the upcoming Olympics. Construction began on a project over a year ago. The stakeholders of the project want a status report on the performance of the project to date. You
Answer: Option A