231. Which of the following processes is involved with identifying which quality standards are relevant to the project and devising a plan on how to meet / satisfy these standards?
  • Perform quality control
  • None of the choices are correct
  • Quality planning
  • Perform quality assurance
Show Answer
232. Which of the following statement are FALSE regarding the probability impact matrix technique?
  • The probability impact matrix specifies combinations of probability and impact that rank the risk as high, moderate and low priority
  • Either descriptive terms or numeric rankings can be used to assign risk rankings to identified risks.
  • In the probability impact matrix the probability and impacts of each risks are accessed against defined scale, and plotted on a two-dimensional grid.
  • Opportunities and threats should not be evaluated in the same matrix concurrently.
Show Answer
233. You are the project manger at a software company developing the next-gen web application server. As software development can be verymnchaotic, your company has elected to follow the more rigorous approach to software development. Specifically, your company haschosen to adopt the Rational Unified Process (RUP) for your current software project. The RUP methodology is highly iterative and produces numerous deliverables include UML diagrams, architecture diagrams, prototypes, and test-cases. You
  • Activity sequencing
  • Activity duration estimation
  • Schedule development
  • Activity definition
Show Answer
234. You are in the process of identifying and documenting the project roles and responsibilities and create staffing management plan. All of the following are tools/ techniques you can use EXCEPT:
  • RBS, OBS
  • Organizational theory
  • RAM, RACI
  • General management skills
Show Answer
235. You are in the process of painting your house. Since you do not want to start painting your house prior to rain storm, you check the weather report to make sure that weather is permitting. Which type of dependency best describes the relationship between the weather and your project?
  • External dependency
  • Discretionary dependency
  • Mandatory dependency
  • None of the choices are correct
Show Answer
236. The risk register is initiated in the Risk Identification process and further updated in the Qualitative Risk analysis and Quantitative Risk analysis processes. Which of the following are NOT risk register updates as part of the Quantitative Risk Analysis process?
  • Prioritized list of qualified risks
  • Residual risk that remain after planned responses are executed
  • Probabilistic analysis of the project
  • Trends in quantitative risk analysis results
Show Answer
237. You are the project manager at Construction Company, assigned to build 30-storey apartment building. In order to being constructing the frame of the building, the foundation of the building must be built. Which of the following relationship types best describes this dependency between framing and foundation?
  • Finish-To-Start
  • Start-To-Start
  • Finish-To-Finish
  • Start-To-Finish
Show Answer
238. You are the project manager at a utility company. Due to the recent rise in the cost of petroleum, your organization is exploring cheaper, alternative forms of energy. You have just completed the project Scope Planning process and created the Scope management plan. However, upon review, you have determined that the resulting project scope management plan is ambiguous and poorly written. A poorly written project scope management plan will directly impact all of the following EXCEPT:
  • Ability to define, prepare and integrate, all subsidiary plan, into the project management plan
  • Ability to formalize acceptance of the project deliverables
  • Ability to create a detailed project scope statement as the basis for future project decisions.
  • Ability to control changes to the project scope
Show Answer
239. All of the following are considered schedule network analysis techniques EXCEPT:
  • What-if analysis
  • Critical chain method
  • Critical path method
  • PDM/ ADM
Show Answer
240. Which of the following processes involves determining what resource and what quantities of each should be used to perform project activities?
  • Activity definition
  • Cost budgeting
  • Cost estimation
  • Activity resource estimation
Show Answer
Questions and Answers for Competitive Exams Various Entrance Test