PMP MCQ Question and Answer

PMP MCQ Question and Answer
61. Which of the following statements regarding Resource Breakdown structure are true EXCEPT:
  • The RBS is a structure that relates the organizational breakdown structure to WBS to ensure that each work component is properly assigned to a responsible person/ team.
  • The RBS is a hierarchical structure of the identified resources by resource category and type
  • The RBS can contain other resource categories other than human resources.
  • The RBS can contain other resource categories other than human resources.
Show Answer
62. You are the project manager for developing a next-generation search engine for internet. Instead of using simple word or link analysis methods, your search engine will use a sophisticated algorithm based on latent semantic indexing. You are in process of creating the detailed project scope statement. All of the following should be included in the detailed project scope statement EXCEPT:
  • Project specification, approval requirements
  • Project boundaries, project deliverables, project acceptance criteria
  • Activity lists, activity attributes, scope baseline
  • Constraints/ assumptions, initial defined risks, schedule milestone
Show Answer
63. Which of the following statements regarding WBS are FALSE?
  • The WBS is deliverable-oriented grouping of project components that define the total scope of project
  • Each item in the WBS is generally assigned a unique identifier that can provide a means to track costs and resources
  • The WBS is used to show which work components have been assigned to which organizational units.
  • The WBS is an output of the Create WBS process
Show Answer
64. Which of the following can be used to display the assigned roles and responsibilities of project team members?
  • PDM
  • GERT
  • ADM
  • RAM
Show Answer
65. You are in process of creating the detailed project scope statement. All of the following are inputs to this process EXCEPT:
  • Project scope
  • Organizational project assets
  • Preliminary project scope statement
  • Scope baseline
Show Answer
66. Which of the following statements are FALSE regarding the Resource Calendar?
  • The Resource Calendar identifies the quantity of each resource available during each availability period.
  • None of the choices are correct
  • The Resource Calendar documents working days and non working days
  • The Resource Calendar provides a hierarchical structure of the identified resources by resource category and resource type
Show Answer
67. All of the statements are true regarding Analogous Estimation EXCEPT:
  • Analogous Estimation is a tool and technique of Activity Definition process
  • Analogous Estimation is a form of expert judgment
  • Analogous Estimation uses the duration of a similar activity to determine duration of current activity
  • Analogous Estimation is also called top-down estimation
Show Answer
68. You are currently in process of prioritizing risks by their impact and probability of occurrence. The risk register updates from this process include all of the following EXCEPT:
  • Root cause of risks
  • Risks group by categories
  • Risks requiring responses in the near term
  • Priority list of project risks
Show Answer
69. The WBS is an input to all of the processes EXCEPT:
  • Scope verification
  • Cost estimating
  • Activity definition
  • Plan purchases and acquisitions
Show Answer
70. You are the project manager for a software company that develops stock analysis software. You have been assigned to assigned to develop a new technical analysis tool to forecast to price of a stock given this historical volatility based on Elliot Wave technique. You need to gather the necessary information to write the project scope management plan. Which of the following information do you NOT need as inputs to your current process?
  • Preliminary project scope statement
  • Project management plan
  • Enterprise environmental factors
  • Project scope statement
Show Answer
Questions and Answers for Competitive Exams Various Entrance Test