PMP MCQ Question and Answer

PMP MCQ Question and Answer
161. All of the following are different dimensions of communication EXCEPT:
  • Precise and accuracy
  • Vertical and horizontal
  • Internal and external
  • Formal and informal
Show Answer
162. Variance analysis, trend analysis, and earned value techniques are:
  • Quality control tools and techniques
  • Process analysis techniques
  • Performance reporting technique
  • None of the choices are correct
Show Answer
163. You are in process of monitoring the various project processes and their performance. Which of the following is the LEAST appropriate tool/ technique to use in this process?
  • Expert judgment
  • Earned value technique
  • Inspection
  • Project management methodology
Show Answer
164. All of the following statements are true regarding issue logs EXCEPT:
  • Issue logs are tools/ techniques of the Develop Project Team process
  • Issue logs are tools/ techniques of the Manage Project Team process
  • An issue log is know as action-item log
  • Issue logs are tools/ techniques of the Manage Stakeholders process
Show Answer
165. Which of the following statements are true regarding random causes and special causes with respect to statistical Perform Quality Control?
  • Special causes area result of variance that are always present in the process
  • Random causes are the result of variance that are linked to unusual events.
  • Random causes are controllable at the operational level
  • Special causes are result of variance that are linked to unusual events
Show Answer
166. Which of the following statements are false regarding project risk management?
  • Risk monitoring and control- track identified risks, monitor residual risks, execute risk response plans
  • Qualitative risk analysis- prioritize risk by their impact and probability of occurrence
  • Risk management planning- decide how to plan and execute risk management activities
  • None of the choices are correct
Show Answer
167. Work performance information is an input to Cost Control process. It includes all of the following EXCEPT:
  • Estimates to complete schedule activities
  • Calculate CV, SV, CPI, and SPI values for WBS components
  • Percent complete of schedule activities
  • Deliverables that have been completed versus not yet completed
Show Answer
168. Which of the following statements are true regarding risk response audits?
  • Risk audits are not necessary on small projects
  • Risk audits should be performed by an outside party
  • Risk audits consists of performing the contingency plan
  • Risk audits are unplanned responses to emerging risks that were previously unidentified
Show Answer
169. All of the following statements are true regarding decomposition EXCEPT:
  • Work should be decomposed to a level where it can be realistically estimated
  • Work should be decomposed to level where it cannot be logically subdivided further
  • Work should be decomposed to a level where it can be performed by one person
  • Work should be decomposed to a level where it can be outsourced or contracted out if necessary
Show Answer
170. You are a project manager at a real estate company that develops and manages commercial, retail and residential properties in South America, Europe, and Asia. As a company continues to grow, the company
  • Review the change request with the change control board
  • Implement the change request as it has little impact to the project and it s easy to implement
  • Review the change request with the project sponsor
  • Investigate options on how to implement the change requests with minimal impact to the project
Show Answer
Questions and Answers for Competitive Exams Various Entrance Test