PMP MCQ Question and Answer
PMP MCQ Question and Answer
31. Three-point estimates are based on determining three types of estimates. Which of the following is NOT one of these estimates?
- Most likely
- Conservative
- Pessimistic
- Optimistic
32. Which of the following statements are FALSE regarding project funding
requirements?
- Funding requirements are derived from cost baselines
- Portions of management reserve can be include in each funding step
- The total funds required are the cost baseline plus the management contingency reserve amount
- Funding usually occurs in incremental amounts that are continuous, and hence appears as S-shaped curves
33. Which of the following processes involves allocating cost estimates in order to establish a cost baseline for measuring project performance?
- Cost estimating
- Cost control
- Activity cost estimating
- Cost budgeting
34. Which of the following statements are TRUE regarding various activity
scheduling tools?
- ADM allows for conditional branching and iteration of activities
- PDM allows for conditional branching and iteration of activities
- PDM uses analogous methods as an estimation technique
- PDM uses activity-on-node (AON) diagramming methods
35. Which of the following are NOT inputs to the risk identification process?
- Historical information
- Risk categories
- Risk management plan
- Risk thresholds
36. Which of the following are NOT outputs of the activity duration
estimating process?
- Updates to activity attributes
- None of the choices are correct
- Schedule baseline
- Activity duration estimates
37. You are in process of identifying and documenting project risks. You are using various information gathering techniques to identify the project risks. All of the following are information gathering techniques
EXCEPT:
- Diagramming techniques
- SWOT analysis
- Root cause identification
- Delphi techniques
38. Which of the following statements are FALSE regarding Monte Carlo analysis?
- Monte Carlo is used to determine potential project outcomes by simulating the project under different scenarios
- Monte Carlo analysis used expected value (EV) calculations as one of its inputs
- Monte Carlo analysis can be used during the Schedule Development and Quantitative Risk Analysis process
- Monte Carlo is simulation technique that can help quantify risks associated with the project
39. You are in process of developing an approved project schedule that will serve as a baseline against which the project can be tracked. Which of the following is needed in order to complete schedule development?
- Requested changes
- Performance measurements
- Approved change request
- Reserves
40. Supporting details for activity cost estimates should include all of the
following EXCEPT:
- Range of possible estimates
- Description of project scope of work
- Documentation of constraints and assumptions
- Performance measurements