PMP MCQ Question and Answer
PMP MCQ Question and Answer
41. Which of the following statements regarding WBS is false?
- To identify the major deliverables of the project requires analyzing the preliminary project scope statement
- The work package is the lowest level in the WBS
- A WBS from a previous project can often be used as a template for a new project
- Different deliverables in the WBS can have different levels of decomposition
42. Roger works for a manufacturer of automotive engines. He has been recently assigned to supervise and mange the manufacturing of a new model of diesel engine. He informs
oger that his new assignment will be to have 500 units of the new diesel engine manufactured in 60 days. Roger is currently in the process of analyzing activity sequences, activity durations, and resource requirements in order to develop the project schedule. Which of the following processed is Roger
performing?
- Activity duration estimation
- Schedule development
- Activity sequencing
- Activity duration
43. All of the following should be included in the initial staffing management plan as part of Human Resource planning EXCEPT:
- Release criteria, recognition and rewards
- Compliance
- Work performance information
- Safety, training needs
44. Which of the following are NOT tools/ techniques of the Plan Contracting Process?
- None of the choices are correct
- Expert judgment
- Screening systems
- Standard forms
45. You are in process of defining how to plan and execute the risk management activities for your project. Which of the following statements are false?
- The output of this process is risk management plan
- The inputs to this process includes the project scope statement, project management plan, and the risk register
- The tools/ techniques of this process are planning meetings and analysis
- None of the choices are correct
46. You are the project manager responsible for developing a new online
line bill payment system for a utility company. You are expected to
complete the project within the next year. You are currently in the
process of identifying and evaluating a number of risks quantifying
their impacts and identifying their probability of occurrence. You would like to use a tool that will determine the highest expected value for the various scenarios. Which of the following tools should you use?
- Monte Carlo simulation
- Decision tree analysis
- Ishikawa diagrams
- Critical path method
47. The CPM calculates the earliest start date, earliest finish date, and latest finish date for each activity. Which of the following statements are true regarding the critical path of a project schedule?
- The float/slack time is determined by subtracting the early start date from the early finish date
- Any project activity with the slack time of zero or greater is considered a critical path tasks
- None of the statements are true
- The float/slack time is determined by subtracting the early start date from the finish date
48. The risk register is an input to all of the following processes EXCEPT:
- Risk response planning
- Risk monitoring and control
- Risk identification
- Qualitative risk analysis
49. You are currently in the process of analyzing activity sequences,duration, resource requirements, and schedule to create the project schedule. Which of the following are not tools/ techniques you can use?
- Crashing, fast-tracking
- Estimating the basis of activity duration by multiplying the quantity of work to be performed by the productivity rate.
- Reallocating resources from non-critical to critical activities
- Calculating theoretical early start/finish dates and late start/finish dates by performing a forward pass and backward pass analysis on project schedule network paths.
50. Assumptions analysis, checklist analysis, and risk diagramming techniques are tools/ techniques of which of the following processes?
- Risk identification
- Qualitative risk analysis
- Risk management planning
- Quantitative risk analysis